The DA Pam 385-64 and the NFPA 780 are used to maintain complete grounding functionality, including static, LPS, and other grounding. We have extensive knowledge and experience in all of these areas.
If you've had lightning strikes in your area or are due for inspections, don't hesitate to contact us.
Taken directly out of the methodology section of our DA Pam CAP plan-
SLP has created Compliance Action Plans (CAPs), which are ready to be used in the field for DA Pam 385-64 compliance. We are ready to go to your installation. Also, check out the Ground Resistance Testing section.
Testing accomplished under DA Pam 385-64 with consideration of NFPA 780 and IEEE-81.
Earth Resistance Testing-Ground testing device-AEMC 4620 utilized for 3-point fall of potential ground testing
and bonding.
Standards of Testing Utilized:
F–1. General requirements LPS will be visually inspected and tested as specified in table 16–1 for electrical
resistance and adequacy of grounding. Any system will be considered deficient if the required resistance value
cannot be met. Any system found to be deficient will be repaired. If the deficiency cannot be corrected
immediately, the LPS test/maintenance/ace personnel must record the deficiency on the test record and
initiate the following actions: a. Notify the installation safety office. b. If the deficient system protects an AE
storage structure, the custodian of the contents must be notified. c. Interim control measures will be
developed based on a risk assessment in accordance with AR 385–10. The risk assessment must consider
ceasing operations in and around the building and rewarehousing the contents for storage facilities. A decision
not to rewarehouse the contents of a storage magazine is justified only when the risk of rewarehousing
exceeds the risk associated with the deficient LPS. When the use of the facility continues, maintenance
to achieve the required resistance must be accomplished as soon as possible.
F–2. Visual inspection of lightning protection subsystem Components of the subsystem will be inspected for the
following: a. Subsystem will meet the requirements specified in NFPA 780. b. Components will not be broken.
c. Components will be in good repair. d. Components will be free of corrosion. Discoloration of materials is not
considered corrosion. e. Components will be free of breaks, cuts, and damage that will affect equipment
integrity. f. Bonding straps will not have more than 50 percent of the wire strands broken, and the remaining
portion of the strap will meet the minimum strap thickness and width/cross-section requirements of table
16–4. g. Components will not be weakened by vibration. h. Components will be securely fastened to their
mounting surfaces and are protected against accidental mechanical displacement as required. i. There
have not been additions or alterations to the protected facility which would require additional protection
or testing.
F–3. Electrical testing of lightning protection subsystems a. Test instruments. Electrical tests consist of
measuring the bonding resistance of the lightning protection subsystem components. The instrument must
be capable of measuring resistance up to 1 ohm +10 percent. The manufacturer’s instruction manual will be
followed to ensure proper use of the instrument. b. Requirements for the bonding test are as follows:
(1) The bonding test (see figure F–1) consists of firmly attaching one lead of the ohmmeter to the down
conductor where it enters the earth. The earth electrode system will be disconnected when practical.
The other lead will then be firmly attached to:
(a) The other down conductor where it enters the earth (see figure F–1).
(b) Each component of the lightning protection subsystem.
(c) Each component of all other subsystems on the facility.
(d) All large metal bodies (a surface area equal to or greater than 400 square inches) that are bonded to the
lightning protection subsystem.
(2) Read the meter. If the meter reading is one (1) ohm or less, the lightning protection subsystem is
acceptable. Record the reading. If the meter reading exceeds one ohm, the lightning protection subsystem is
not acceptable.
(3) If lightning protection down conductors are not accessible, the air terminal base may be used as an alternate
reference test point for the meter test lead. The air terminal selected should be the same one used to do the
3-point fall of potential test, which validates the system’s resistance to earth.
Requirements:
15-2 Building
f. Each magazine will be provided with appropriate means of lightning protection in accordance with chapter 1
6, Section IV
16–5. Electrical service lines in ammunition and explosives areas a. Each service line will be run underground
from a point at least 50 feet away from the building. The exterior line side of the main disconnecting switch or
circuit breaker must have suitable lightning arrestors. See paragraph 8–14 and table 8–1 for separation distance
for electrical lines. b. Surge (lightning) arresters will be required and installed as specified in NFPA 70,
Article 280.
16–6. Low voltage utility lines Local telephone service and similar low voltage intercom or alarm systems must
also comply with the same underground routing for the last 50 feet. Surge protection, even for lines that run
underground, will be provided to shield against any severe electrical surges from a nearby lightning strike or
excessive power through the line from other outside sources, such as broken power lines. Surge suppression
for incoming conductors must include suppression at the entrance to the building from each wire to ground.
16–11. Ordnance grounds
Ordnance grounds are used to ensure that electric currents do not flow between
ordnance components when they come in contact or are assembled. These currents can be produced by
common mode voltages induced in-ground loops, ESD of one component into another, and potential
differences created in the facility's ground system due to direct lightning strikes or near misses.
a. Ordnance grounds are electrically separated from all other ground systems (and objects connected to other
grounding systems). At former Navy installations, ordnance grounds and ground subsystems may be
connected to the secondary ground girdle at a single point.
b. Where they exist, ordnance grounds will be maintained.
16–13. Ammunition and explosives facility grounding
a. AE facilities will be provided with a ground system to provide personnel, equipment, and facility protection.
Personnel safety is provided by low impedance grounding and bonding for personnel, equipment, DA PAM
385–64 • 24 July 2023 131 metallic objects, and piping to prevent voltages sufficient to cause a shock hazard
or initiate AE within the facility.
b. A facility ground system is composed of the earth electrode subsystem and one or more of the following